Thursday, March 6, 2014

Association work

Exterior Building Painting Schedule:


Building        Dates
    18          2/10 thru 4/18
    32          4/21 thru 5/30
    33          6/2 thru 7/11
    37          7/14 thru 9/26
    35          9/29 thru 11/25



The buildings will remain open during painting and guests will be notified of the work.



Termite Tenting Schedule

Building        Dates
    34            9/8-10
    21            9/9-11

The buildings will be out of order during the termite tenting.

The expense of these projects is covered by the Associations' regular building and maintenance budget and will not require any specially assessments.  All the rental programs have been notified of these upcoming projects.
Any questions should be directed to Gana Maheshwaran at 808-742-3557
or by email to:
gana.maheshwaran@outrigger.com 



Thanks,
Randy Danto Nordstrom
randy@kiahuna39.com