The onsite portion of the Kiahuna Infrastructure Study is in progress and should be completed on or before Feb 7th. Coffman Engineering, lead by Tom Looney is doing the work with the help of Dennis Bonilla's team, and preliminary reports for Buildings and Grounds Committee are due by February 21st. Final reports are due to AOBO before March 14th.
Any questions should be sent to:
scott.tiraschi@gmail.com
Wednesday, January 29, 2014
Tuesday, January 28, 2014
Pathway between Kiahuna and Koa Kea
Dennis Bonilla has worked very hard with others, including Scott Tiraschi, to get the pathway between Kiahuna and Koa Kea to become a reality.
We learned that the concrete pathway is now a paved path!
We learned that the concrete pathway is now a paved path!
Sunday, January 19, 2014
meeting information
1:00PM – 5:00PM Outrigger Rental Committee Executive Session
1:00PM Building & Grounds Committee Meeting
2:00PM Pool & Baseyard Committee Meeting
3:30PM Insurance Committee Meeting
4:00PM Planning and Policy Committee Meeting
4:30PM Legal Committee Meeting
5:30PM Resort Operating Committee Meeting
6:30PM AOBO Executive Session with dinner
SATURDAY, FEBRUARY 8, 2014
8:00AM-9:00AM AOBO Executive Session
9:00AM – 11:00AM Outrigger Rental Owner Session
11:30AM-12:30PM Homeowner Luncheon
12:30PM – 5:00PM Quarterly Meeting of the AOBO Board of Directors
5:00PM-6:00PM Complimentary Homeowner Reception
Fruit & Cheese Display
(2) Drink tickets for beer or wine
HOTEL INFORMATION
Doubletree Hotel San Francisco Airport
835 Airport Boulevard Burlingame, CA 94010
650-344-5500 www.sanfranciscoairport.doubletree.com
Room Rate $139 (subject to availability)
Complimentary Breakfast Buffet Coupons for hotel guests at the 37 North Restaurant
Complimentary in-room internet
$10 local & overnight parking
Thursday, January 16, 2014
AOBO meetings
This is a little reminder that the AOBO meeting is Feb. 8th in San Francisco.
There is a homeowner lunch at 11:30 A.M. followed by the Quarterly Meeting of the AOBO Board of Directors starting at 12:30.
The agenda is being prepared and I will post it as soon as I receive it.
The hotel arrangements are still being worked out. I will give you the information on that as well. We encourage all homeowners to attend the meeting!
Any questions should be sent to Marianne:
marianne.thesken@outrigger.com
Randy
There is a homeowner lunch at 11:30 A.M. followed by the Quarterly Meeting of the AOBO Board of Directors starting at 12:30.
The agenda is being prepared and I will post it as soon as I receive it.
The hotel arrangements are still being worked out. I will give you the information on that as well. We encourage all homeowners to attend the meeting!
Any questions should be sent to Marianne:
marianne.thesken@outrigger.com
Randy
Wednesday, January 8, 2014
Painting schedule (exteriors)
Building 17-- Jan 6 - Feb 7
Building 18 - Feb 10 - Apr 18
Building 32 - April 21 - May 30
Building 33 - June 2 - July 11
Building 37 - July 14 - Sept 26
Building 38 - Sept 29 - Nov 25
Any questions should be directed to Marianne Thesken
Marianne.thesken@outrigger.com
Randy
Wednesday, January 1, 2014
Twin Bridges pool vote
Happy New Year to everyone. We wish you health, happiness and all good things for 2014!
The results for the Twin Bridges pool voting are in.
The majority of those voting (including the non-votes, which are considered a "NO" vote) were opposed to putting a pool in that location. A 67% vote in favor was required to go forward.
Here is the tally from Marianne:
The results for the Twin Bridges pool voting are in.
The majority of those voting (including the non-votes, which are considered a "NO" vote) were opposed to putting a pool in that location. A 67% vote in favor was required to go forward.
Here is the tally from Marianne:
Yes
|
77
|
45.0%
|
No
|
68
|
39.8%
|
Did Not Vote
|
26
|
15.2%
|
Total Phase II Units
|
171
|
100%
|
This means that we are back to the base yard location for our pool, as that location was previously approved by the Phase II owners some years ago.
It is expected that a proposed plan for the design, construction costs and timeline will be presented to homeowners at the annual May meeting in Kauai. Estimates will also be included for the new Maintenance Yard in that area.
To incur new costs and provide for the improvements for a pool, we need to have 67% of all homeowners vote in favor of it, since that constitutes a change in the common elements. A non vote is a no vote.
To borrow money, we need approval of 50% of the homeowners. That is a separate vote.
Scott Tiraschi is heading up the pool committee so if you have any questions, please refer them to him: Scott.Tiraschi@gmail.com
Randy Danto Nordstrom